Kirkland street work schedule altered due to heavy rains

Fifteen residential streets in the Market, Norkirk, Bridle Trails and South Rose Hill neighborhoods that were originally scheduled for closure on Aug. 13 will remain open today, thanks to wet weather.

Fifteen residential streets in the Market, Norkirk, Bridle Trails and South Rose Hill neighborhoods that were originally scheduled for closure on Aug. 13 will remain open today, thanks to wet weather.

Rain forced Kirkland’s slurry seal contractor to postpone until Aug. 18 the work scheduled on those streets.

 

The rescheduled street sections in the Market and Norkirk neighborhoods are:

7th Avenue West, from 4th Street to 2nd Street

10th Avenue West, from 4th Street to Market Street

11th Avenue West, from 4th Street to Market Street

16th Avenue West, from 8th Street to 6th Street

17th Avenue West, from 6th Street to 8th StreetWest

1st Street, from 19th Avenue to 20th Avenue

3rd StreetWest, from Market Street to 5th Avenue

6th StreetWest, from 17th Avenue to Market Street

 

The rescheduled street sections in the Bridle Trails and South Rose Hill neighborhoods are:

117th Avenue Northeast, from Northeast 75th Street to the north end of the Street

118th Avenue Northeast, from Northeast 75th Street to the north end of the Street

119th Avenue Northeast, from Northeast 74th Street to Northeast 75th Street

123rd Avenue Northeast (two sections), from Northeast 61st Street to Northeast 62nd Street

124th Avenue Northeast, from Northeast 65th Court to the end of the Street

Northeast 75th Street, from 116th Avenue Northeast to 120th Avenue Northeast

Northeast 74th Street, from 119th Avenue Northeast to the west end of the Street

Northeast 65th Court, from 122nd Avenue Northeast to 124th Avenue Northeast

Northeast 62nd Street, from 122nd Avenue Northeast to 123rd Avenue Northeast

Northeast 61st Street, from 122nd Avenue Northeast to 123rd Avenue Northeast

 

The wet weather forecasted yesterday also forced Kirkland’s slurry seal contractor to reschedule to Aug. 19 work on sections of 17 neighborhood streets in the Bridle Trails and South Rose Hill neighborhoods. Those postponed sections are:

117th Avenue Northeast (two sections), from Northeast 70th Street through 117th Drive Northeast

117th Drive Northeast

119th Avenue Northeast, from Northeast 68th Street to Northeast 67th Place

120th Avenue Northeast, from Northeast 70th Street to Northeast 75th Street

123rd Avenue Northeast, from Northeast 78th Street to Northeast 75th Street

126th Avenue Northeast, from Northeast 66th Place to Northeast 68th Place

128th Place Northeast, from Northeast 75th Court to the north end of the cul de sac

131st Avenue Northeast (two sections), from the south end of the cul de sac to Northeast 80th Street and from the end of the Street to Northeast 83rd Street

Northeast 66th Place, from 126th Avenue Northeast to the east end

Northeast 67th Place, from 119th Avenue to the eastern hammerhead

Northeast 68th Place, from 122nd Avenue Northeast to the western hammerhead

Northeast 73rd Street, from 120th Avenue Northeast to 122nd Avenue Northeast

Northeast 76th Street, from 128th Place Northeast to 130th Avenue Northeast

Northeast 78th Street, from 123rd to 122nd Avenue Northeast

Northeast 128th Street, from Northeast 128th Streetto the end of the Street